The Harris County Flood Control District provided an update to Harris County Commissioners Court on November 12, 2026, highlighting progress on federally funded flood risk reduction projects and outlining efforts to maximize available funding. The presentation, delivered by Executive Director Marcus Stuckett, also addressed upcoming grant deadlines, potential project adjustments, and opportunities to keep federal investments working for Harris County residents.
Understanding the Role of Federal Funding
Federal grants are an important source of funding for projects that help reduce flood risk throughout Harris County. Two programs play a significant role in these efforts:
- Community Development Block Grant for Disaster Recovery (CDBG-DR): Supports recovery efforts following major disasters, including projects that address damage and flooding impacts.
- Community Development Block Grant for Mitigation (CDBG-MIT): Supports long-term improvements designed to reduce the impacts of future disasters.
These programs are funded through the U.S. Department of Housing and Urban Development and administered through the Texas General Land Office (GLO).
The Flood Control District works with federal, state and, county partners to advance eligible projects while meeting grant requirements and spending deadlines.
Progress in Project Delivery
During his presentation, Director Stuckett highlighted improvements in the pace of construction and project delivery.
Since the previous update to Commissioners Court on June 11, construction production has increased sixfold. In October alone, the Flood Control District recorded approximately $19 million in construction spending and submitted $55 million in reimbursement requests to the GLO.
Director Stuckett also confirmed that all projects currently included in the CDBG-DR portfolio are expected to be completed.
These improvements reflect ongoing efforts to move projects through construction and make use of available federal resources.
Addressing Remaining Funding Challenges
Despite this progress, the Flood Control District continues to evaluate how to maximize federal grant funding before program deadlines.
Under the announced one-year grant extensions, the November presentation identified approximately $113.4 million in projected unallocated CDBG-DR funding, assuming certain Harris County Housing and Community Development projects are excluded, and approximately $207 million in projected unallocated CDBG-MIT funding.
These figures represent funding that may remain unused under current project plans and timelines. They do not mean the money has already been lost or that an equivalent amount of projects has been canceled.
The Flood Control District is evaluating several options to make use of these resources, including transferring eligible projects between grant programs and identifying additional work that could qualify for funding.
For example, the Upper Cypress Creek Floodplain Preservation project and Lauder Stormwater Detention Basin Phase 3A are being considered for transfer into the CDBG-DR program.
Other projects may require adjustments to their planned scope or funding sources depending on available grant extensions.
These options remain under consideration and are subject to applicable GLO approvals.
Why Grant Deadlines Matter
Flood risk reduction projects often require years of planning, engineering, environmental review, right-of-way acquisition, and construction.
Grant deadlines can affect how much work can be completed within a funding program. When timelines are limited, projects may need to be divided into smaller construction phases, adjusted or supported through alternative funding sources.
The Flood Control District’s presentation demonstrated how additional time could help preserve planned improvements.
For CDBG-MIT, a two-year extension through March 31, 2030, could reduce projected unallocated funding from approximately $207 million to $48 million. A three-year extension through March 31, 2031, could potentially allow the full allocation to be used if additional eligible projects are included.
These longer extensions have not been approved.
Having greater certainty about grant timelines would allow the Flood Control District to make informed decisions about project designs, construction schedules and available resources.
For residents, these decisions matter because funding availability and project timelines directly influence when improvements intended to reduce flood risk can move forward.
Commissioners Court Approves Next Steps
Following the presentation, Commissioners Court unanimously approved two motions aimed at identifying additional funding opportunities and supporting ongoing project delivery.
The first directs the Flood Control District to work with Harris County Housing and Community Development, the Office of the County Engineer, and the Department of Intergovernmental and Global Affairs to identify additional ways to use existing federal funding.
The working group is expected to return to Commissioners Court with recommendations by February 11, 2027.
The second motion directs county officials to seek state and federal support for preserving Harris County’s federal disaster recovery and mitigation allocations.
Neither motion approved new grant extensions or project transfers. Those decisions will require additional coordination and review.
To learn more about these programs, visit hcfcd.org/CDBG.
The Flood Control District will continue working with its partners to advance eligible projects, address funding challenges, and pursue opportunities to reduce flood risk throughout Harris County.