Construction activities include contractor mobilization, initial site preparation, and other related work. Residents are urged to respect all warning signs.
About this Project
The Taylor Gully Channel Conveyance Improvements and Woodridge Stormwater Detention Basin project, Phase 1, consists of approximately two miles of channel conveyance improvements and a wet-bottom stormwater detention basin that is designed to provide approximately 412 acre-feet of stormwater storage capacity.
That is roughly the equivalent of 412 football fields covered in one foot of water.
Funding
- The 2018 Bond Program is expected to contribute approximately $3.1 million.
- The grant application for this project was approved to receive up to $41.9 million through the Community Development Block Grant – Mitigation (CDBG-MIT) program, provided by the U.S. Department of Housing and Urban Development and administered by the Texas General Land Office.
- The project is receiving $8.35 million in funding from the Environmental Protection Agency and federal Community Project Funding secured by Congressman Dan Crenshaw.
- The project is receiving $10 million in funding from the Texas Water Development Board in partnership with the City of Houston.
- The construction contract was awarded for approximately $29.4 million.
- This project is located in the Kingwood area.
The Flood Control District is coordinating with Montgomery County on the drainage easement needed to support construction access, drainage improvements, and long-term maintenance activities associated with the Woodridge Stormwater Detention Basin project.
Anticipated Schedule
- Construction Start: Q2 2026
- Construction Completion: Q4 2027
The Flood Control District appreciates the support of federal, state, and local partners as the implementation of flood risk reduction projects continues across the San Jacinto River watershed.
Submit a question or comment about this project!
The Flood Control District is continuing to make historic progress in flood risk reduction projects and maintenance efforts thanks to voter support and dedicated staff. Stay informed by following us on social media.