Construction activities include contractor mobilization, initial site preparation, and other related work. Construction crews will be accessing the site from multiple locations along Greens Bayou between John F. Kennedy Boulevard and Aldine Westfield Road.
About this Project
The Greens Mid-Reach Channel Conveyance Improvements Project – Segment 1 consists of conveyance improvements on approximately five miles of…
Construction crews will be accessing the site at Miranda Street and Maximilian Street. Residents are urged to respect all warning signs.
About this Project
Phase 2 of the Lauder Stormwater Detention Basin consists of two dry-bottom compartments. Phase 2, Compartment 1 was completed in Q2 2025. Compartment 2 is expected to provide approximately 260 acre-feet of additional…
The Harris County Flood Control District is working to reduce flood risks along the mid-reach stretch of Greens Bayou. The Greens Mid-Reach Program is a long-term multi-project initiative along Greens Bayou from Veterans Memorial Drive to JFK Boulevard. The program is intended to improve channel conveyance along Greens Bayou and provide stormwater storage capacity within…